Structural steel up, electrical rooms advancing, first Rolls-Royce mtu packages in place — the campus moves toward first power in 2027.
Generation halls · summer 2026Summer construction at AHI is at full pace. Structural steel is up on the generation halls, electrical rooms are advancing, and the first Rolls-Royce mtu packages are in place on their rails.
The sequence from here is energy first: gensets and mechanical, then the electrical and motor-control-centre energization sequence, then fibre and network, then hall fit-out. Milestones are published in the newsroom as they land.
Alberta trades are on site through each phase, hired locally first. The buildings are precast and sound-walled — an as-built design that goes beyond the modelled acoustic design.
First power remains targeted for 2027, with the first Secure Data Halls ready for racks and GPUs in the same year. A separate grid interconnection is in development.
AHI — AI Hub of Innovation is developed by Havenz Smart Communities (Lead Developer) in partnership with Turning Stone Developments (investment partner); both are general partners of AHI. Statements about future capacity, dates and milestones are forward-looking and subject to approvals, capital and change; nothing in this article constitutes an offer to sell or a solicitation of an offer to buy securities. Growth beyond the first phase is a master-plan objective subject to its own permits and studies. Third-party names describe roles and imply no endorsement. See Important information.

Havenz Smart Communities, the developer, and Turning Stone Developments, a Métis-owned company, are general partners of AHI — one flagship, one standard.

A County industrial park at the seam of Red Deer, Red Deer County and Blackfalds — on a transportation corridor that is getting bigger.

Lasting local benefits · no electricity costs shifted · minimal water · transparency · strategic value to Canada — five national expectations, and how the campus lines up.